C-K Approves Order Changes, Votes to Seek Proposals for Athletic Project Work

At its Nov. 9 meeting, the Claysburg-Kimmel School Board approved some change orders that add an additional $53,843 to the cost of the district’s athletic project. L.S. Fiore, the project’s contractor, requested and received approval of $4,633.68 to remove a pavement low spot and adjust the grade for drainage; $40,496.68 to install 15-inch pipe from Athletic Drive to the Rain Garden; and $8,713.37 to remove unusable soil and install structural fill for the bleacher foundations. Board Vice President Craig Burket was the lone no vote.

The board also authorized the administration to seek proposal...

 